Metro In Tricity of Chandigarh, Mohali and Panchkula:-
• Route length – 37.573 Kms, out of which 6.406 Kms falls in Haryana.
• Total project cost – Rs 13,909 crore, out of which investment to be made of GoH is Rs 1802 crore.
• Memorandum of Understanding between GoI, UT Chandigarh, Govt. of Punjab and Govt. of Haryana has been signed in july,2015.
• As per DPR, construction work was to be started in April, 2016. Commercial Operation is proposed to start from April, 2021.
• Corridor-I: Capitol complex, Chandigarh to Gurdwara Singh Shaheeda, Mohali – 12.497 Kms.
• Corridor-II: Transport Terminus (Mullanpur) to Grain Market, Sec. 20, Panchkula -25.076 Kms.
Length/Cost details:
|
Length (in Kms.)
|
Estimated cost (Rs in crore)
|
Chandigarh portion
|
23.362
|
10018
|
Punjab portion
|
7.805
|
2089
|
Haryana portion
|
6.406
|
1802
|
Total
|
37.573
|
13909
|
• Project has not been found feasible
DPR