Gurugram Metro Project (executed by DMRC):-
• Total Length -14.47 km – 7.05 km falls in Haryana, 7.42 km falls in Delhi
Cost- Rs 1477 crore. Haryana segment–Rs 743 crore, Delhi Segment–Rs 734 Crore
• Stations – Haryana Segment-5 Nos. i.e Guru Dronacharya, Sikanderpur, MG Road, IFFCO Chowk, HUDA City Centre
Delhi Segment-5 Nos. (all elevated) i.e. Qutab Minar, Chhatarpur, Sultanpur, Ghitorni, Arjangarh
• The line is in operation since September, 2010
Funding pattern:- (Rs in crore)
Particulars
|
GOH
|
GOI
|
DMRC
|
Total
|
Cost of land
|
20.00
|
-
|
-
|
20.00
|
Cost of network (excluding taxes in the ratio of 80:20)
|
456.00
|
1114.00
|
-
|
570.00
|
Interest free SD for Central taxes to be shared between GOH & GOI in the ratio of 20:80
|
11.00
|
44.00
|
-
|
55.00
|
State Taxes
|
Exempted by GoH
|
-
|
-
|
-
|
Cost of rolling stock
|
-
|
-
|
98.00
|
98.00
|
Total
|
487.00
|
158.00
|
98.00
|
743.00
|
Delhi Segment:- |
(Rs) |
Cost Of Construction |
734 Crore |
Land Cost |
49 Crore (Shared by GNCTD and GoI as subordinate debt) |
Main Debt |
352 Crore |
Equity by GNCTD/GoI |
333.00 crore |
In the interest of early commissioning of the project, GoH has contributed 1/3rd of the equity of Rs 111.00 crore as grant in the cost of Delhi segment.