Gurugram Metro Project (executed by DMRC):-

• Total Length -14.47 km – 7.05 km falls in Haryana, 7.42 km falls in Delhi Cost- Rs 1477 crore. Haryana segment–Rs 743 crore, Delhi Segment–Rs 734 Crore

• Stations – Haryana Segment-5 Nos. i.e Guru Dronacharya, Sikanderpur, MG Road, IFFCO Chowk, HUDA City Centre Delhi Segment-5 Nos. (all elevated) i.e. Qutab Minar, Chhatarpur, Sultanpur, Ghitorni, Arjangarh

• The line is in operation since September, 2010

Funding pattern:- (Rs in crore)

Particulars

GOH

GOI

DMRC

Total

Cost of land

20.00

-

-

20.00

Cost of network (excluding taxes in the ratio of 80:20)

456.00

1114.00

-

570.00

Interest free SD for Central taxes to be shared between GOH & GOI in the ratio of 20:80

11.00

44.00

-

55.00

State Taxes

Exempted by GoH

-

-

-

Cost of rolling stock

-

-

98.00

98.00

Total

487.00

158.00

98.00

743.00


Delhi Segment:- (Rs)
Cost Of Construction 734 Crore
Land Cost 49 Crore (Shared by GNCTD and GoI as subordinate debt)
Main Debt 352 Crore
Equity by GNCTD/GoI 333.00 crore

In the interest of early commissioning of the project, GoH has contributed 1/3rd of the equity of Rs 111.00 crore as grant in the cost of Delhi segment.

#
#